At what point does a contractor need to schedule a driveway inspection?
  • A "Culvert Grade Set" inspection must be scheduled prior to the purchase or installation of a culvert.
  • A "Culvert Install" inspection must be scheduled following the installation and backfill of the driveway culvert.
  • A "Driveway Pre-Pour" inspection must be scheduled after the driveway formwork and reinforcement is in place, before any concrete has been poured.
  • A "Driveway Post-Pour" inspection must be scheduled after the driveway has been poured, formwork has been removed, and any washout containers and clean up has been completed.

Show All Answers

1. Who is responsible for maintaining sidewalk and driveways?
2. When is a grading permit required?
3. Do I need a permit to cut down a tree?
4. Is slit fence required for all construction sites?
5. What are the requirements for storm sewer materials?
6. What size culvert do I need for a driveway that will be installed?
7. Who handles a complaint about high grass on a property or excessive amount of trash?
8. How do I schedule an inspection for my driveway permit or grading permit?
9. At what point does a contractor need to schedule a grading inspection?
10. At what point does a contractor need to schedule a driveway inspection?
11. What permit is required for a lane closure, barricades in the street, or a street cut?
12. My ditch needs to be cleaned out or 'mopped out'?
13. My sewer is backing up. What should I do?
14. Can you install a stop sign to slow down traffic?
15. Can a "Slow - Children at Play" sign be installed?
16. How do I report a streetlight that is out, or request a new light to be installed?
17. Is a permit needed to install a fence?
18. What is the process to install Fiber Optic Cables in the public right-of-way and City easements?
19. What is a road diet?